Municipal records can reveal a major project before a company names itself. They can also create false confidence. A hearing is not necessarily approval. An agreement can carry conditions and repurchase rights. A planning body can recommend approval before the applicant withdraws. A groundbreaking does not freeze the original scope or schedule.

The useful questions are narrower: which parcel is involved, which body acted, what did that body actually do, what conditions survived, and what happened next?

Six parcel-level decision arcs

Later status reflects official sources checked through August 2, 2026.
CaseExact site identityStage-correct readingLater status
Project Osprey, RosemountParcel 340321065011 and adjoining land east of Robert Trail SouthA comprehensive-plan hearing proposed new guidance, not building approvalHome Depot distribution center completed and in use
Project Bigfoot, RosemountAbout 280 acres east of Dakota County Technical CollegeA delay for environmental-review timing was not a rejectionApproved and under construction; not company-confirmed operating
Microsoft, Mount Pleasant315 acres in TID 5 with road and rail boundariesApproved agreements retained conditions, deadlines, and repurchase rightsFirst facility operating; second under construction
Deep Meadow Ventures, IndianapolisEleven addresses covering 467.66 acresCommission certification did not create a durable final entitlementWithdrawn
Agincourt, ValparaisoOption on about 180 acres of a larger city-controlled siteTemporary site control and due diligence, not an application or approvalTerminated before entitlement application
VinFast, Chatham County2357 Moncure Flatwood Road and broader bounded siteLand control and groundbreaking did not preserve the original schedule or planRevised plan filed; facility not operating

Project Osprey: a hearing became a working distribution center

Rosemount, Minnesota published an April 2021 hearing notice for a comprehensive-plan amendment associated with Project Osprey. It identified parcel 340321065011 and adjoining land east of Robert Trail South and proposed changing guidance from Community Commercial to Business Park for a future warehouse and distribution center.

That record established a parcel, proposed use, and hearing date. It did not authorize construction. By November 2021, the city reported that the Council had approved a development agreement the prior month and that work had begun on a 70-acre Home Depot distribution site. The city's development history describes required road access.

Rosemount's 2024 financial report records the 2021 Home Depot agreement and lists the center among principal employers. The defensible chain is hearing, later agreement, infrastructure, construction, and use, not approval at the hearing.

Project Bigfoot: a delay was not a rejection

Rosemount moved its December 19 Council meeting to December 21. At the December 21 meeting, the Council adopted the UMore AUAR update and approved Jimnist LLC's Project Bigfoot plans. The sequence supports a short procedural pause followed by approval, not a rejection.

The approved application covered about 280 acres east of Dakota County Technical College, as described on the city's development page. Meta identified itself on March 14, 2024.

The city later reported construction. Meta's current location page lists a 2024 groundbreaking and describes jobs expected after completion. No company source located by the cutoff said the facility was serving traffic. The supported status is approved and under construction, not operating.

Mount Pleasant: approval retained deadlines and remedies

In March 2023, Mount Pleasant approved agreements involving Microsoft and a 315-acre site in Tax Incremental District 5. The site was described south of Braun Road, north of County Highway KR, east of the Canadian Pacific rail right of way, and west of 90th Street.

The municipal fact sheet set a July 1, 2026 deadline for the first phase and July 1, 2033 for the second. If Microsoft failed to begin required buildings by those dates, the village and county could repurchase the relevant land at the original per-acre price.

On June 23, 2026, Microsoft said its first facility was operational and a second adjacent facility remained under construction. The agreement was material early evidence, but one operating facility does not mean every planned phase is complete.

Indianapolis: certification still ended in withdrawal

Deep Meadow Ventures proposed a data center on 467.66 acres across eleven Indianapolis addresses. It sought rezoning and variances including additional building height and setback relief. The April 10, 2025 hearing agenda recorded an automatic continuance requested by a registered neighborhood organization.

The Metropolitan Development Commission approved the case at its August 20 hearing and issued a certification report dated August 26. The proposal was then called out for a council hearing, postponed while withdrawal was pending, and acknowledged as withdrawn by the commission on October 1. The City-County Council formally acknowledged the withdrawal on October 6.

An intermediate body can recommend approval without producing a durable final entitlement. The final status is withdrawn.

Valparaiso: a land option was only a feasibility window

In January 2025, the Valparaiso Redevelopment Commission approved an option allowing Agincourt Investments to examine about 180 acres near the former St. Mary Medical Center. The mayor's official account listed unresolved power, water, test-well, zoning, environmental, amenity, development-agreement, and purchase questions.

The option represented temporary site control and a right to investigate. It was not a development application, zoning approval, or construction authorization. On March 13, the commission terminated the option and released escrow, as recorded in the official packet and minutes. Officials said no project had been approved or presented.

VinFast: the site remained while the plan changed

Chatham County's current land record identifies VinFast Manufacturing US LLC as the owner of parcel 0005623 at 2357 Moncure Flatwood Road and lists a 2022 deed in book 2318, page 0414. VinFast held a groundbreaking on July 28, 2023 and then described an approximately 1,800-acre plant with production expected in 2025.

On July 12, 2024, VinFast changed the expected production date to 2028. A revised plan narrative dated March 25, 2026 describes a 236-acre multi-building manufacturing campus within a larger site.

The document supports a precise status: VinFast retained site control and filed a materially revised plan after delaying production. It does not establish final approval of the revised plan or operation of the factory.

A better status sentence

A useful site-selection record should read:

[Project] at [parcel or address] reached [stage] on [date]. [Body] [exact action] concerning [instrument]. Remaining conditions include [conditions]. Later official status as of [date]: [status].

That structure prevents a hearing from becoming approval, an option from becoming entitlement, and a groundbreaking from becoming an operating facility.

What this audit supports

  • Parcel numbers, address sets, and stable geographic boundaries can link changing codenames and applicant entities.
  • Action verbs identify materially different entitlement stages.
  • Conditions, deadlines, repurchase rights, and outside reviews can change the meaning of approval.
  • Later official records can resolve construction, operation, revision, withdrawal, and termination.

What it does not support

  • The cases do not estimate project success, failure, timing, market demand, or investment value.
  • A development agreement does not prove every land-use, utility, or construction approval is complete.
  • Site control is not an entitlement, and a comprehensive-plan amendment is not a building permit.
  • A company schedule or expected completion date can change after the cutoff.
  • The six purposefully selected cases are not representative.

Sources and method

Sources were checked through August 3, 2026. Each event was coded as inquiry or option, application or hearing, advisory recommendation, final approval, executed agreement, construction, operation, revision, withdrawal, or termination.

  1. Project Osprey: hearing notice; later city update; 2024 city financial report.
  2. Project Bigfoot: December 5 meeting record; December 21 approval record; city development and identity page; Meta identification.
  3. Mount Pleasant: municipal fact sheet; agreement approval; company status.
  4. Indianapolis: hearing agenda; adopted MDC minutes; MDC certification and report; Council withdrawal record.
  5. Valparaiso: option and due-diligence statement; termination minutes.
  6. VinFast: county land record; groundbreaking; delay update; revised plan narrative.

This is a public-record site-selection example. It is not an entitlement opinion, engineering or utility study, title review, project forecast, or investment recommendation.